DREDGING OF CONTAMINATED SEDIMENT AT BADGER ARMY AMMUNITION PLANT,
GRUBER'S GROVE BAY IN LAKE WISCONSIN
by Bay West, Inc.

Aerial view of
Badger AAP Site
(Photo courtesy Bay West, Inc.)
Under the U.S. Army
Corps of Engineers' Omaha District's Total Environmental Restoration
Contract (TERC) 5, for which Bay West, Inc. is a team subcontractor
to Stone & Webster, Inc., Bay West was contracted to dredge sediments
from Gruber's Grove Bay, located off the Wisconsin River near the Badger
AAP site (vicinity of Baraboo, Wisconsin), where munitions components
were formerly manufactured up until 1972.
Initial Investigation & Winter
Sampling
Bay West initiated work at the site in the winter of 1999 by
performing an investigation of sediments in the frozen 20-acre bay to
identify the extent of mercury-impacted sediments. Sediment probes were
used to determine the thickness of sediments at more than 500 locations.
As a cost efficient approach, work was completed in the winter when the
lake was frozen; this way, surveyors could stake sample locations and
the sample crews could move easily between areas, in comparison to using
boats. Using a combination of geoprobing for discreet core sampling,
and hand-operated grab and core samplers, Bay West collected and sampled
sediment cores at 1-foot intervals. The crews were able to complete each
location in less than half the time originally estimated. As a result,
Bay West saved the client nearly $50,000.
Dredging Activities
Dredging of the impacted sediments took place throughout the
spring and summer and fall and is scheduled to be completed late November
2001. Utilizing an Mud Cat Mud Cat™ MC-2000 hydraulic auger
dredge, Bay West dredged approximately 90,000 cubic yards of impacted
sediments. The Mud Cat™ MC-2000 utilizes a 24-inch (609 mm) diameter,
22,000 pound torque horizontal auger to combine sediments and water into
a slurry that will be hydraulically pumped through 4,500 feet (1,372
m) of 10-inch (254 mm) pipeline. The dredge was able to take 2 foot depth
cuts in the forward direction and 1.5 foot cuts in the reverse operation. Aerial
surveillance of the dredge showed virtually no turbidity plume. This
is typical when using the MC-2000 in fine, colloidal sediments.

Mud Cat™ MC-2000 Dredging Mercury-Contaminated Sediments
from Gruber's Grove Bay - Making Final 5 Passes to Complete Project
Samples of the water
taken at the sprayheads showed only 5 parts per billion of mercury,
and well below the Wisconsin DNR design parameters.

North end of lay down area,
geo containers stacked 3 high
The ability of the
MC-2000 to cut out sediment while operating in the reverse direction
reduced dredging site time considerably. Approximately 105 of
the tubes were filled, a larger amount than planned, and the MC-2000
pumped in excess of the 90,000 cubic yards. Even with the excess
yardage the job was completed on time during 2001.

Mud Cat™ MC-2000
Dredging at Badger Army Ammunition Plant
Gruber's Grove Bay in Lake Wisconsin
(Photo courtesy Bay West, Inc.)
Dewatering/Disposal
The sediments were dewatered through the use of large geotextile
fabric containers (geotubes) placed in a lined and bermed dewatering
basin, called a Laydown Area. The 105 geotubes, each 200 feet (61 m)
long and 20 feet (6 m) in diameter, were pumped full of slurry at a rate
of 1,500 gpm, until the tubes were full of sediment. Water from the sediments
was pumped through another pipeline and discharged over 20 acres of pastureland
via spray irrigation techniques. Tests indicated less than 5 PPB
of mercury in irrigation water which is below WDNR State standards.

Filled Tubes with Pinch System Inset

Spray Irrigation System for
water collected from geo containers
For more information, contact:
Sales
Department
Phone: 410-545-0261
Fax: 410-545-0293
|