|
Mud Cat
Case Study
Mud Cat™
DREDGING '94
Proceedings of the Second International Conference on Dredging
and Dredged Material Placement:
The Welland River Dredging Demonstration
Philip Miles,
P. Eng. (Senior Geotechnical Engineer, Acres International
Limited, Niagara Falls, Ontario, Canada)
Donald Marr, P. Eng. (Manager, Engineering and Environment,
Atlas Specialty Steels, Welland, Ontario, Canada)
Abstract
A dredging demonstration was carried out in the Welland River to test
a sediment removal technology being considered for a full scale cleanup.
The demonstration involved the controlled removal of 127 m3 of
industrial mill scale and contaminated sediment using a modified
Mud Cat™ MC-915 ENV dredge. Contaminants consisted of several metals,
phosphorus and oil and grease which exceeded provincial sediment
quality guidelines. Dredge modifications focused on minimizing the
resuspension of contaminated sediment while maximizing the solids
content of the dredgeate and included a special auger head and boom
assembly, a new traversing winch assembly, new dredge sponsons, and
conversion capability for the dredge to accept standard Mud Cat components.
Dredging parameters were monitored and recorded using dredge mounted
instrumentation and a data logging system.
Project Background
In the late 1980s, investigations in the Welland River in the City
of Welland, Ontario, Canada identified a 1.25-km stretch of the
river, which contained a significant volume of industrial contamination
and contaminated river sediments resulting from past discharges
by Atlas Specialty Steels (Atlas), other local industry and the
city.
In the late 1990, a
proposal was accepted by Environment Canada's Great lakes Cleanup Fund
for partial funding of a small dredging demonstration under the Contaminated
Sediment Removal Technology Demonstration Program (CSRTDP). The demonstration
project was the first carried out under CSRTDP. A second successful
proposal was accepted by the Cleanup Fund for partial funding of a
treatment demonstration under the Contaminated Sediment Treatment Technology
Program (COSTTEP). The dredging and treatment demonstrations were carried
out concurrently.
Site Description
and Contaminant Characterization
The dredging site was located on the lower reach of the Welland River.
The width of the Welland
River varies from approximately 40 to 60 m. The maximum depth of water
is approximately 4 m. Historical average river flow ranges from approximately
14.2 m3/s in June/July to 24.6 m3/s in March,
corresponding to current velocities of 0.15 to 0.26 m/s. Due to downstream
flow controls, the river undergoes apparent flow reversals on a daily
basis.
Past industrial discharges
through the McMaster Avenue and another nearby downstream outfall have
resulted in two accumulations of reef-type deposits of oily, black,
fine to coarse granular, metallic industrial mill scale, totaling approximately
5000 m3. The maximum thickness of the industrial deposits
is approximately 2.5 m.
Approximately 25 000
m3 of clay and silt river sediments have also been variably
impacted by the contaminated discharges.
The mill scale and
the contaminated sediments contain concentrations of several metals,
including copper, chromium, iron, lead, manganese, nickel and zinc,
as well as phosphorus and oil and grease which exceed the Ontario Ministry
of the Environment and Energy (OMOEE) sediment quality guidelines (OMOE,
1991).
Description
of Sediment Removal Technology
The main components of the sediment removal technology were the dredge
and the piping system used to convey the contaminated slurry to the
NFP, the dredge instrumentation, and the silt curtain which was installed
at the dredge site.
The selected equipment
was expected to meet the following design requirements:
- minimize sediment
resuspension in the water column to protect downstream water quality
- remove contaminants
without excessive removal of clean sediment
- handle excavation
of cohesive clayey silt sediment
- function under existing
river flow and site conditions
- maximize solids
concentrations in the dredged material
- operate at reasonable
production rates
- be compatible with
a continuous flow, high volume treatment technology
- contain and transport
dredged material between the dredging site and the treatment site.
Modified Mud
Cat Dredge
The Mud Cat dredge, manufactured by Mud Cat International (Mud Cat)
of Baltimore, MD, USA, was selected as the preferred dredging technology
for the demonstration. It is built to operate in shallow marine environments
and features an effective sediment removal system consisting of a boom-mounted
horizontal auger and a centrifugal slurry pump. The dredge was relatively
easily modified to include innovative components designed to satisfy
the environmental demands of the project.
The Mud Cat MC-915
model was selected as the basic dredge for the demonstration. The class
of material to be dredged and the depth of operation were within the
capabilities of the MC model and in addition, with its slurry pump
located between the hulls, it offered more scope for required boom
and auger modifications. The specially prepared MC-915 ENV (ENV=Environmental)
dredge incorporated modified components which were initially designed
and fabricated by Mud Cat for the demonstration. It retained many
features of the standard MC-915 dredge including working capacity,
engine, drive, pump, hydraulic system, electrical system and propulsion.
The dredge underwent preliminary wet performance testing at a facility
in Baltimore. Subsequent modifications were made by the Atlas in Welland.
The following modifications
were incorporated into the dredge.
- Special MC-915 ENV
auger head and boom assembly:
- one auger
head with hydraulic forward tilt and manual transverse tilt
capability
- one dual-convergence,
variable-pitch, multi-flight auger
- full rear
shroud behind auger
- Removable vibrating
front shroud including:
- removable
front screens
- top mounts
for vibrating motors
- Special MC-920 type
truss boom assembly including suction hose
- Hydraulic equipment
package including:
- auger head
tilt indicator
- two variable
control hydraulic vibrators
- auger reducer
and motor
- boom winch
system
- New depth gauge
scale
- Assorted connecting
hardware for system
- Complete double
wrap traversing winch assembly
- Two new trunnions
with pins
- Two new sponsons
to support boom assembly
- Conversion capability
to accept standard MC-915 components as required.
The piping system to
convey the dredged material to the treatment facility consisted of
a floating section of 200-mm diameter flexible butyl rubber hose and
rigid polyethylene (PE) pipe connecting the dredge to a slurry sampling
station located on shore, 1500 m of land-based fused-jointed PE pipe
and a booster pump.
Instrumentation
In order to assess the project and the dredge performance, an instrumentation/data
logging package was added to the dredge. Analog displays provided
the dredge operator with real-time indicators of dredging performance.
The instrumentation included:
- one nucleonic densitometer
with spool piece
- one electromagnetic
flowmeter
- one dredge head
vibration sensor
- one dredge head
turbidity sensor
- analog displays
for slurry velocity, slurry density, vibration, and production rate
- one dredge cab-mounted
data logger with 4 input channels complete with IBM PC compatible
support software, cable and NEMA 4 enclosure
- connecting hardware
and cables to link the data logger to sensors and a remote portable
computer
Silt Curtain
Structure
A commercially available silt curtain was selected for the project
and was modified by the manufacturer to meet specific demonstration
requirements. It consisted of an impermeable polyester-reinforced vinyl
fabric which extended the full depth of the water column. Segmented
foam flotation members were fabricated into the full length of the
top edge.
Demonstration of Technology
The demonstration involved the removal and treatment of approximately
127 m3 of industrial mill scale and contaminated sediment
from within the silt curtain. Dredging was carried out in a downstream
to upstream direction only. The bank of the river was not disturbed;
however, dredging along the sloping river bottom was carried out.
The successful completion
of the project involved the coordination of a variety of activities
which enabled both the dredging technology and the treatment technology
to be demonstrated concurrently.
The dredging program
was controlled by Operational and Performance Standards which were
issued by Environment Canada (Environment Canada, 1991) as criteria
for evaluating the dredging technology. It considered three categories,
namely sediment removal, transport and pretreatment. The main concerns
under sediment removal are the containment of resuspended contaminants
and removal efficiency. No dredging was carried out until the enclosing
silt curtain had been installed.
The modified MC-915
ENV dredge was first tested in uncontaminated sediment within the silt
curtain just upstream of the McMaster Avenue outfall, proving that
the technology could be used with little environmental impact. Dredging
in contaminated sediment commenced in late October. Five to eight test
runs per day were conducted and evaluated over the next 12 days.
The operating procedures
required that daily activities be coordinated to optimize both dredging
time and data acquisition. Each test run also required synchronization
with the sediment treatment plant and the booster station operation,
with regard to start and stop of dredging and flow rate control.
Dredging started in
the 'original' mode and during the course of the dredging, numerous
planned modifications were made to the dredge and the operating procedures
to allow evaluation of the dredge in terms of slurry production yields
and turbidity. The impact of each modification on sediment resuspension
inside and outside the silt curtain was monitored as part of the water
quality monitoring program. These modifications included:
- removal of the shroud
screens ('screen off' mode) to reduce 'ploughing' of the sediment
in front of the dredge head. The screens did not allow passage of
weeds and cohesive sediments
- welding small steel
bars across the suction intake to minimize the entry of debris
- installation of
a check valve in the pipeline at the dredge discharge to minimize
backflow
- relocation of the
shroud vibrators in an effort to impart a more horizontal action
to the head.
Midway through the
demonstration the modified auger was replaced with the standard toothed
auger and near the end of the demonstration the auger shroud was removed
('shroud off' mode').
In the early stages
of dredging, all operating parameters for any given test run were kept
as nearly constant as possible. As dredging progressed, a more flexible
control of the dredging equipment by the dredge operator was adopted
('Variable Q' mode) allowing him to change parameters such as engine
speed, advance rate and depth of cut during a test, in order to maximize
sediment removal. This operating procedure resulted in less standby
time for the dredge and an increase in the number of test runs per
day in the latter part of the demonstration program.
Conclusions
The Mud Cat technology was successful in removing contaminated sediment
from the riverbed and transporting the sediment to the treatment
site and was well suited to the site conditions, even though slurry
density and percent solids were less than had been anticipated. The
field modifications made to the dredging equipment during the project
allowed assessment of its performance and specifically determination
of the impact of the modifications on sediment resuspension and on
dredge productivity. The conclusions from the dredge evaluation are
summarized as follows.
- The vacuum suction
of the dredge played a major part in minimizing resuspended solids.
No sustained plumes of resuspended material propagating away from
the dredge head were observed. High turbidity levels during 'pump
off' conditions are attributed to movement of the dredge between
runs and to backwashing through the pipeline.
- Dredging in the
'original' mode resulted in an overall average turbidity of 18.5
FTU (Formazin turbidity units) at the dredge head compared to background
turbidity of 5 FTU. Dredging in the 'shroud off' mode with the standard
auger resulted in an overall average turbidity of 17.6 FTU. Operating
in the more flexible 'Variable Q' mode resulted in longer periods
of dredging and less frequent plugging of the pipeline while still
maintaining low turbidity levels at the dredge head (overall average
13.8 FTU). Operating in the 'screen off' mode resulted in the lowest
turbidity levels at the dredge head (overall average 5.4 FTU) but
also resulted in frequent blockage of the intake or dredge pump.
- The intake screen
on the dredge head limited the movement of sediment, especially the
cohesive clayey silt, to the auger.
- The overall average
percent solids (by weight), including mill scale and river sediment,
in the pumped slurry was low (2.1%, excluding rinsing) and varied
considerably during the demonstration due to the structure of the
dredging program (with frequent starts, stops and flushing of the
pipeline) and the generally cautious approach to the dredging to
minimize environmental concerns. Also, the dredge head did not tilt
transversely, as designed, and dredging across the sloping river
bottom did not allow even entry of sediment into the dredge head.
- Some of the field
modifications to the dredging equipment had a significant affect
on the slurry solids production rate. The removal of the intake screen
increased the overall average percent solids to 3.7% while the removal
of the dredge head shroud resulted in the highest overall average
percent solids of 4.4%. Peaks averaging 22% solids in the 'shroud
off' mode are indicative of the maximum achievable production rate.
- The shroud-mounted
vibrators did not have a significant positive affect on dredge performance.
- The mill scale was
dredged at a higher percent solids that the river sediments. Based
on the evaluated data, 10% solids (by weight) is identified as a
conservative estimate of the average percent solids achievable during
full-scale dredging in mill scale using the 'shroud off' (or comparable)
mode. A conservative estimate of 5% solids has been identified as
achievable for the river sediments. Dredging across the river, instead
of parallel to it, should also yield a more efficient sediment removal.
- TSS concentrations
at a distance of 10 m away from the dredge were well below the Environment
Canada criteria of 25 mg/L at a distance of 25 m. The maximum TSS
concentration measured a distance of 10 m away from the dredge was
21 mg/L.
- The Gheen couplings
on the flexible section of the pipeline were not sufficient to eliminate
leakage of slurry without the addition of Victaulic clamps.
- The instrumentation
and data logger installed on the dredge provided reliable data for
real time monitoring of the dredging operation. The cab-mounted displays
of slurry density and flow allowed the dredge operator to optimize
the sediment removal process.
- The silt curtain
performed well with regard to the containment of river sediment that
became resuspended during the dredging demonstration. No evidence
of a downstream impact of the dredging was measured.
Acknowledgments
The authors wish to acknowledge the participation of Environment Canada,
the OMOEE, the Niagara River Remedial Action Plan Public Advisory
Committee and the local Welland River Cleanup Committee. Partial
funding by Environment Canada and the OMOEE is also acknowledged.
References
Ontario Ministry of the Environment, 1991. The Provincial Sediment
Quality Guidelines (Draft). Water Resources Branch, Toronto.
Environment Canada, 1991. Operational and Performance Standards.
Environmental Protection, Ontario
by Carol Ancheta |