|
-
|
|

Mud Cat Case Study
Mud
Cat™
Sludge Removal Problems Solved Successfully
Problem
Sludge removal problems, at one time difficult to solve, are now being
handled in stride by specialized cleanout contractors. For Lukens Steel,
the challenge was to clean out a 20-million-gallon industrial cooling
reservoir in Coatesville, Pennsylvania, which had a 30-year accumulation
of sediment.
Solution
Lukens' contractor, Mobile Dredging& Pumping Company (Chester, PA)
used a transportable dredge, a Mud Cat™ SP-915, and four transportable
belt press systems to:
- Dredge the basin to 21 feet, twice the typical cleanout depth.
- Prevent
the sediment, once disturbed, from dispersing and ultimately getting
into the plant to possibly stain Lukens' manufactured products.
In-water dispersal was minimized first by a hydraulically-operated
mud shield that confined the agitated material to the area surrounding
the
dredge auger and its pump intake, and by contractor-placed solid-vinyl
silt curtains deployed between the plant-water pump intakes and the
dredging operation.
- Reduce the volume that had to be off-hauled. This
was achieved by the efficiency of the contractor's four mobile belt
presses which, from an
incoming 7 to 8 percent solids, produced a completely landfill-acceptable
sludge cake of 50 to 60 percent (versus the usual 15 to 20 percent).
- Protect
the environment, particularly from spillage, via a four-way solution
involving:
- Staging sludge slurry feed tanks and the four trailer-mounted
press systems on a bermed asphalt containment area.
- Providing a solid loading surface for the dewatered sludge
by temporarily paving the area below the press
delivery chutes with 4 inches of asphalt
and placing movable concrete barrier walls behind
them to help contain the cake.
- Equipping sludge haul trucks with tailgate locks to prevent
accidental discharge of dewatered sediment.
- Carefully coordinating feed of the dredged slurry
through two-way radios between dredge operator and
shore technicians,
thus minimizing chances
of overfilling.
The contractor's portable hydraulic dredge, a Mud
Cat™ SP-915,
removed bottom deposits, 3 to 4 feet thick,
consisting of solids from equipment washdowns
plus sand and
dirt pumped in with
river water used
to replace water lost in evaporation-type
cooling. By specification, removal operations
were conducted
while
the reservoir and
all manufacturing operations continued
to function. At
work, the Mud Cat's™ auger-type
cutting head mechanically moved a slurry
of water and sediment through a self-contained
trash pump and
a floating pipeline. Its working path was controlled by a winch system
that guided the rig along a cable successively moved to closely-spaced
shore anchor points located at the opposite sides of the 180' x 1000'
concrete-lined reservoir. A controlled flow of 800 gpm ended up in two
ground-based portable tanks, each 21,000 gallons in capacity, which acted
as surge storage facilities between the dredging and dewatering operations.
Within the tanks, mixers rotated non-stop to homogenize the mix and
keep the particles in suspension, ensuring a consistent feed to the trailer-mounted
twin-belt filter presses.
Four of these portable units did the dewatering, the number having been
selected to match dredge capacity and the desired production schedule.
Sludge pumps on each press were set to draw the volume required to keep
output to an optimum level. Each 2.5 meter press was capable of handling
up to 200 gpm. Input was adjusted through a manifold to match the varying
incoming sludge percentages.
A granular organic water treatment polymer was fed in from four 500-gallon
tanks; the additive conditioned and flocculated the sediment. From here,
the mixture was channeled between sets of porous filter belts under increasing
pressures applied by a series of rollers. This pressure forced out almost
all the free water, producing a sludge cake more than half solids that
was conveyed to a chute for deposit onto a ground-level staging area.
The material was then loaded by a small conventional tractor shovel into
dump trucks and removal accomplished by hauling the material through
plant property and over state highways to disposal at a plant-owned state-approved
industrial landfill.
Mobilization was completed within five working days of the starting
date, and reservoir cleaning was completed 70 working days later. The
schedule was attained as planned by working one 10-hour shift per day,
six days per week. Demobilization was completed within six working days
after the reservoir was cleaned.
Results
Project pricing was based on capacity restored to the reservoir, not
on the amount of dewatered material generated, which eliminated such
variables as the amount of dewatered sludge generated, its solids content,
and the volume of dewatering conditioners used. Thus, Lukens Steel
did not pay for additional weight or volume caused by lower-than-anticipated
solids content or higher-than-anticipated conditioning agents. The
project was successful in providing Lukens Steel with an additional
5 million gallons of cooling water storage capacity.
Reprinted from The National Environmental Journal
|
|